About this informed Mayor Vitaliy Klitschko on the air of “Kyiv 24”.
"We will not launch the metro by the end of the year, but some stations will not be open, but almost built. That is, the intensity of work is going on. And we plan to implement this extremely important project by the end of next year," the mayor quoted his own position on the air.
At the same time, in October 2025, the mayor statedthat at least one metro station will be opened in 2026.
We remind you that the Kyiv city government and the Kyiv Metro Public Enterprise filed lawsuits to JSC “Kyivmetrobud” – the former contractor for the construction of the metro on Vynohradar. According to the results of the examination, the company caused losses to the Kyiv community of over 2,3 billion UAH due to disruption of the work deadlines, another 1,36 billion UAH are fines and penalties.