About this said press service of the KMDA.
According to the results of the examination, the company caused losses to the Kyiv community of over UAH 2,3 billion due to disruption of the work deadlines, another UAH 1,36 billion in fines and penalties.
Experts also found that a significant part of the work performed was not properly documented. In 2023, the city terminated the contract with Kyivmetrobud due to the excessively slow pace of construction.
In 2024, a new contractor, Avtostrada, was selected and work resumed. The construction of the first phase of the metro to Vynohradar — 3,7 km of track and two stations, Mostytska and Varshavska — is currently ongoing around the clock.